31.03.2014 - A contract no. L-APV-14-0077 was signed with LIAA. Total project costs 687'037.99EUR;
09.05.2014 - First three machines have been delivered for a total sum of 299'959.00EUR. within the                            project with contract no. L-APV-14-0077. With this investment, GRANITS Ltd. increased                              production capacity by 40%;
18.08.2014 - A contract no. L-APV-14-0165 was signed with LIAA. Total project costs 518’205.00EUR;
10.10.2014 - Fourth machine has been delivered for a total sum of 64'130.00EUR within the project                              with contract no. L-APV-14-0077
03.11.2014 - Fifth machine has been delivered for a total sum of 89'540.00EUR within the project with                         contract no. L-APV-14-0077 
16.03.2015 - First two machines have been delivered within the project with contract no. 
                       L-APV-14-0165
27.03.2015 - Last two machines have been delivered for a total sum of 233'409.00EUR within the
                       project with contract no. L-APV-14-0077 
07.04.2015 - 30% prepayment has been made to suppliers account for delivery of last machine within                        Project with contract No. L-APV-14-0165
19.10.2015 - Last machine has been delivered for a total sum of 190'800.00EUR within the
                       project with contract No. L-APV-14-0165
05.09.2017 - A contract no. 1.10.-19/2017 was signed with MASOC Competence center for a research
       no. 1.10. Total project costs 232'970EUR